This document is the release note of SEPA Payment Suite. It describes only the aspects which are new or have been enhanced, updated or removed since the previous release.
The version R23.10 of the application SEPA Payment Suite has been developed from March 2023 to August 2023. The delivery on external acceptance (available for customers) will begin on the 13th of September 2023 and the delivery on production will start on the 16th of October 2023.
Releases schedule
You will find below the schedule of next releases of 2023 :
-
SPS Creditor : R23.10 (previous version : R23.4)
-
SPS Signature : R23.10 (previous version : R23.4)
These are the current defined milestones. The final deadlines will be sent at each beginning of release period.
We let you take note of:
-
The period dedicated to customers’ requests for each version: we recommend to notify us of the change requests as soon as possible for a higher chance to be included in the release.
-
The customer acceptance phase will begin one month before the delivery on production. The communication of bugs will last three weeks. Final date to raise bugs is the 6st of October 2023. Official validation of acceptance and validation for delivery on production will start on the 16th of October 2023.