Introduction

This document is the release note of SEPA Payment Suite Signature. It solely describes the new features implemented on SPS-Signature, or the features that have been enhanced, updated or removed since the previous release.

The version R22.10 of the application SPS-Signature has been developed from April 2022 to August 2022. The delivery on external acceptance (available for customers) will begin on the 19th of Septmeber 2022 and the delivery on production will start on the 17th of October.

Releases schedule

You will find below the schedule of next releases of 2022:

  • SPS Creditor : R22.10 (previous version : R22.4)

  • SPS Signature : R22.10 (previous version : R22.4)

These are the current defined milestones. The final deadlines will be sent at each beginning of release period.

image

We let you take note of:

  • The period dedicated to customers’ requests for each version: we recommend to notify us of the change requests as soon as possible for a higher chance to be included in the release.

  • The customer acceptance phase will begin one month before the delivery on production. The communication of bugs will last three weeks. Final date to raise bugs is the 7th of October 2022. Official validation of acceptance and validation for delivery on production will start on the 10th of October 2022.